Zoning and Specific Use Permits
- Zoning Verification Letter: 7 to 10 business days
- Zoning Applications
- Change of Zoning: Two months
- Change of Zoning - Planned Development: Two to Four months
- Specific Use Permit: Two months
- House Conversion: Two months
Plat Applications
- Working Plat Only Review: 7-9 business days
- Working Plat with Construction Plans: 10-12 business days
- Final Plat: Five weeks
- Replat: Five weeks
- Preliminary Plat: One month
Variance Applications
- Variances One month from filing deadline
Board of Adjustment
- Variances One month from filing deadline
Site Permit & Schematic plans
- Schematic Plans: 7-9 business days*
- * Applicable for certain zoning cases as identified in the Pre-submittal meeting notes
- Site Engineering and Public Plans: 10 to 12 business days
Building Permits
The following permits are reviewed while you wait:
- Accessory/storage buildings
- Carports
- Demolition
- Driveway repair/installation
- Electrical
- Foundation repair
- Irrigation
- Mechanical
- Plumbing
- Patio covers
The following permits are reviewed and action is taken within 14 business days:
- Additions
- All apartment work
- Churches
- Interior completions
- Non-residential remodels